How to build an accurate prebuild
A prebuild is your price for one unit of work, like a square metre of decking. Build it right once and every quote that uses it comes out right.
A prebuild is your price for one unit of work: a lineal metre of wall frame, a square metre of decking, one door hung. Measure the plans, multiply by the prebuild, and the quote writes itself. Get the prebuild wrong and every quote that uses it is wrong the same way, job after job, until someone notices the margins.
Here’s how to build one properly, using a square metre of decking as the example.
The five steps
- 1Pick the unit you measure off the plansEach, per lineal metre or per square metre. Use the unit you take off in, so the quantity on the plan drops straight onto the price. Decking is measured in m².
- 2Price the materials for one unit, plus wasteBoards, joists, fixings and finish for one square metre, at what you actually pay, plus your waste allowance. In the example that comes to $140 a square metre including 10% waste.
- 3Get the hours from your own jobsNot from a book and not from memory. The last three decks took 52, 43 and 45 hours for 38, 30 and 32 m²: 140 hours for 100 m², so 1.4 hours a square metre.
- 4Cost those hours at what an hour really costs youAbout $86 an hour in our example, not the $45 wage (the real hourly cost guide shows the maths). 1.4 hours × $86 is $120.40 of labour, so the cost is $260.40 a square metre.
- 5Add your marginFor a real 20% margin, divide by 0.8: $260.40 ÷ 0.8 is $325.50 a square metre. Adding 20% would only give you 16.7%; the markup versus margin guide explains why.
- Materials, including 10% waste
- $140.00
- Labour: 1.4 h × $86
- $120.40
- Cost
- $260.40
Example figures, ex GST.
Then every quote is a multiplication
Once the prebuild is right, the price of any deck is the area off the plans times $325.50:
- 24 m² deck
- $7,812.00
- 40 m² deck
- $13,020.00
- 18 m² deck
- $5,859.00
Ex GST. Every one of them carries the same 20% margin.
Check it after every job
A prebuild is a prediction. After each job, put the actual hours next to it. If the last deck took 1.6 hours a square metre instead of 1.4, that’s $17.20 a square metre of labour you didn’t price in, on every deck you quote until you fix it. Update the prebuild and the next quote is right.
A few habits that keep prebuilds honest
- Keep supply and install as separate items, so install-only work gets the right price.
- Put fixings, consumables and site clean in the build-up or as their own allowance lines. Don't leave them to the margin.
- Price the hard version separately: working at height, poor access, a second storey. A first-floor wall frame takes longer than a ground-floor one.
- Work in minutes per unit for labour. 84 minutes a square metre is easier to check against a timesheet than 1.4 hours.
- Quote ex GST and show the GST on the quote.
A $45-an-hour carpenter costs about $86 for every hour on the tools once you add on-costs, leave, lost days and overheads. The maths, step by step.
Adding 20% to your costs gives a 16.7% margin, not 20%. How markup and margin differ, the divide-by table, and what it costs you over a year.
Lay your quote out by floor level, itemise every line and attach take-off sheets that show what's in and what's out. A layout builders can check fast.
Run these numbers on every job, without the spreadsheet.
XGrafter prices every take-off from your own rates, keeps the margin in front of you, and syncs with Xero (MYOB is coming). See it on one of your own jobs.